How to track design hours by stage in an MEP or architecture firm

By Indravadan Vala, MEP consultant (15+ years) and founder of AECVeda · 4 November 2026

Most design firms know their fee for a project. Very few know what each stage of that project actually cost them in hours. That gap is where margins quietly disappear, and it is the reason the next fee proposal is a guess again. Here is a simple way to close it, written from fifteen years of running MEP projects.

Why stage-wise hours matter

A typical fee is split by stage: concept, design development, tender or good-for-construction (GFC) drawings, and site support. If you only track total hours per project, you find out you are over budget when the project is nearly finished, too late to do anything about it. Tracked by stage, the same hours tell you three useful things:

Step 1: Fix your stage list, and keep it short

Use the same stages as your fee schedule, so hours and fee line up. Five to seven stages is enough. A common list for MEP consultancies is:

  1. Concept and design basis report (DBR)
  2. Schematic design
  3. Design development
  4. Tender / good-for-construction (GFC) drawings
  5. Shop drawing review and site support
  6. As-built review and handover

Architecture and interior firms will use their own names, but the rule is the same: one list for the whole firm, matching the way you bill.

Step 2: Add disciplines and a few work categories

In a multi-discipline firm, stage alone is not enough. HVAC, electrical, plumbing and fire may each be on budget except one, and the total hides it. Record the discipline with every entry.

Then add a handful of work categories that explain why hours were spent: design, drawing, coordination, site visit, and, most importantly, client-requested revisions. That last category is the evidence you need when you ask for additional fees.

Step 3: Turn the fee into an hour budget per stage

Before work starts, convert each stage's fee into hours:

Budget hours for a stage = (stage fee × target cost share) ÷ average hourly cost

For example, if the GFC stage fee is ₹4,00,000, you aim to spend 60% of fee on staff cost, and your average cost is ₹800 per hour, the GFC budget is 4,00,000 × 0.6 ÷ 800 = 300 hours. Share that number with the project lead. A budget nobody sees is not a budget.

Step 4: Make the weekly timesheet painless

Stage-wise data is only as good as the timesheets behind it. Three habits make the difference:

Step 5: Review hours against budget every month

Once a month, for every live project, compare hours spent with the budget for each stage, and note the percentage of drawings or deliverables complete. A simple traffic-light rule works well:

Step 6: Close the loop on the next proposal

When a project ends, record the actual hours per stage against its size (area, number of keys, beds or floors). After a handful of projects you will have your own benchmarks, such as hours per 1,000 m² for the GFC stage of a commercial building, and your fee proposals stop being guesses.

A quick checklist

Doing this in Excel? That works for a few people. As the team grows, a tool built for it saves the chasing. AECVeda TMS records hours by stage and discipline from weekly timesheets, with approvals and hours-against-budget reports, set up for architecture, MEP and other design firms. Free for teams of up to 3, with a 14-day trial of everything.